Project Description
Client: Gibson Electric/Clune Construction
Location: Chicagoland Suburb, IL
Completion Date: 2026
John Burns Construction is proud to support the T5@Chicago III project—under the direction of Gibson Electric and Clune Construction—by self-performing the underground utility and assisting with the site electrical services.T5 Data Centers is developing T5@Chicago III, a premier 250,000-square-foot, three-story data center located in Northlake, Illinois which will provide 36 megawatts of IT capacity.
Scope of Work
- Excavation, concrete pouring, and backfilling for all electrical and telecommunication duct banks
- Stub-up conduit installations into the building at POE (Point of Entry) rooms
- Assisting electricians with conduit installation throughout the duct bank system
- Excavation and installation of power and telecommunication vaults
- Construction, forming, and pouring of concrete racks and 90s for transformers
- Conduit proofing to ensure system integrity
- Excavation and concrete work for light pole foundations
- Splicing and erecting site lighting