Buffalo Grove – AT&T Duct Bank Relocate

Project Description

Client: AT&T
Location: Buffalo Grove, IL – 1000’ of Buffalo Grove Road on South Dundee Road
Year Completed: 2009
Value: $175,000

The Challenges

  • As part of a forced conduit relocation for AT&T, John Burns Construction Co. (JBCC) was able to save the customer 65% off of an internal budget.
  • JBCC worked with Civil Tech to design offset foundations around AT&T Duct in order to complete this IDOT contract without disrupting AT&T facilities.
  • JBCC’s price of 175K was $325,000 lower than competitive pricing provided by AT&T.
  • JBCC works at present with the Illinois Department of Transportation, Chicago Transit Authority,
    O’Hare Modernization Program and others to complete direct bid work throughout the State of Illinois. We believe that on future projects such as this we may be able to help AT&T again.

STREAM Data Center Electrical & Telecom Conduit Installation

Project Description

Client: Titan Electric
Location: Elk Grove Village, IL
Year Completed:  2020
Value: $682,293.00

The Challenges

  • Project scope included installing conduit duct banks of various sizes which will eventually feed generators and transformers that will power the data center facility.
  • Approximately 1,600 Lf of duct bank installed with varying package size (2-5”, 16-4”, 2-2”, 1-1.5”)
  • All work was completed in close quarters with several other trades working in the same areas to meet the customer’s tight schedule.
  • Worked to complete conduit installation inside and outside of building.

CTA 77th & Kedzie Street Bus Garage Project

cta1

Project Description

Client: Chicago Transit Authority (CTA)
Location:  Chicago, Illinois
Year Completed: 2018
Contract Value: $6,825,000

The Challenges

  • Design-Build of a Bus Washer System at the 77th Bus Garage for washing of 250+ buses per day
  • High Speed Doors at the 77th Bus Garage and the Kedzie Bus Garage.
  • Building Automation System to interconnect the Bus Washer System, High Speed Doors, and electrical components to be run as one Unit.
  • Civil Construction consisting of new concrete slab, underground plumbing system, lead paint removal and asbestos abatement, masonry tuckpointing & repairs, painting, completely new HVAC exhaust fans, unit heaters, plumbing system, electrical and Building Automation System throughout the Bay.

Traffic Signal Modernization

Project Description

Client: City of Chicago
Location: Chicago, Illinois
Value: $1,900,000
Year Completed: 2009

The Challenges

John Burns Construction Company upgraded three total traffic signal systems in the three busiest traffic signal intersections in the City of Chicago, March 2009 valued at $1,900,000.

  • Upgrade traffic signals in three busiest intersections in Chicago: 89th Street and Stony Island; 91st and Stony Island: Milwaukee Avenue – Nagle Avenue – Devon Avenue.
  • Installed new traffic signal poles, controllers, countdown pedestrian signal heads, vehicle detection cameras, sidewalk, asphalt, pavement marking and landscaping.
  • Completed project during off-peak time and nighttime hours in order to reduce the overall impact on the traveling public.

Stony Island Bridge and Roadway Rehabilitation

Project Description

Client: Illinois Department of Transportation
Location: Chicago, IL(Stony Island Interchange)
Year Completed: 2015
Value: $3,200,000

John Burns Construction Company completes the Stony Island Bridge and Roadway Rehabilitation project in March, 2015 installing lighting, camera towers and intelligent highway systems.

The Challenges

  • Drill and install 175 light poles with associated conduit and foundations.
  • Installation and removal of a temporary lighting system to provide lighting throughout the duration of the contract.
  • Placement of approximately 6 miles of fiber optic cable.
  • Installation of 5 – 80′ CCTV camera tower and foundations.
  • Replacement of existing traffic surveillance system.
  • Relocation and replacement of existing dynamic message sign power and communication equipment.

Statesville Prison High Mast Tower Replacement

prison

Project Description

Client: State Of Illinois, Capitol Development Board
Location: Joliet, Illinois
Year Completed: 2011
Contract Value: $250,000

John Burns Construction Company successfully completed the removal and installation of high mast towers for Statesville Prison in Joliet, Illinois in 2011.

The Challenges

  • Removal of nine (9) existing High Mast Towers inside Statesville Prison property.
  • Installation of nine (9) new 100’ High Mast Towers on existing foundations.
  • Project required close coordination with Statesville Prison personnel to allow for normal operation of prison activities.
  • Project schedule required completion of all work within ten (10) working days.
  • Removal, installation, testing and turnover was completed by JBCC in five (5) working days.

Wacker Drive Lighting Installation

Project Description

Client: James McHugh Construction joint venture with Araiza Corporation
Location: Chicago, Illinois
Value: $22,000,000
Year Completed:   2012

The Challenges

John Burns Construction Company completed the installation of new traffic signal equipment, cameras and new architectural lighting along Upper Wacker Drive.

  • JBCC completed the installation of new traffic signal equipment at all seven intersections along Upper Wacker from Randolph to Van Buren.
  • Installed new traffic equipment at Van Buren & Wells to add a contra flow right turn lane from Van Buren to Wells.
  • Installed new traffic equipment at Wells & Harrison along with Harrison & Wacker/Franklin to coincide with the congress interchange opening. 
  • JBCC also installed all new architectural lighting along Upper Wacker Drive to match the lighting which was previously installed on the East/West section of Upper Wacker Drive. 
  • Due to the new lane configuration and clearer separation of the service lanes from the through lanes, JBCC installed new traffic signals at Lower Wacker & Adams, 20 S Lower Wacker Drive, Lower Wacker & the Monroe on Ramp, and 155 N Lower Wacker Drive. 
  • JBCC was required to cut loops into the pavement for vehicle sensing on all of the intersections on Lower Wacker Drive and installed cameras for sensing on all of the intersections along Upper Wacker Drive.

Wacker Drive – Viaduct Reconstruction

wacker drive viaduct

Project Description

Client: McHugh – Araiza Joint Venture
Location:  Chicago, Illinois
Year Completed:   2012
Contract Value: $22,000,000

John Burns Construction Company successfully completed the Wacker Drive Reconstruction Projects for the Chicago Department of Transportation as the electrical subcontractor to the McHugh – Araiza Joint Venture. The reconstruction was split into two contracts both encompassing a similar scope. Phase I was the complete reconstruction of Lower and Upper Wacker starting at Randolph and continuing south to Monroe. Phase II picked up where Phase I left off at Monroe, continued south to Van Buren and tied into the newly reconstructed Congress Interchange. Both of these projects were a continuation of the work completed in 2001 on the East/West portion Upper and Lower Wacker Drive. JBCC worked closely with the GC to ensure our work was completed on time and in sequence to meet the contract required milestones. JBCC’s scope was very large with a wide variety of activities starting from the underground infrastructure to the installation of the traffic signals. The following is a list of our scope highlights:

The Challenges

  • Utilidor Construction: The Utilidor was the installation of a 32 cell concrete encased duct bank package running the entire length of the reconstructed Wacker Drive. The installation also included 6 cell concrete encased duct bank laterals running from the mainline near the utility entrances of various buildings. At some locations the utilidor was up to 20’ below the proposed Lower Wacker Drive Pavement. In addition to the duct bank packages JBCC was responsible for the installation of specially constructed precast manholes weighing approximately 30,000 lbs each. These larger manholes were used as tie in points for the laterals which terminated near the buildings at precast manhole weighing approximately 18,000 lbs each. JBCC was responsible for all shoring required making the excavation safe for the installation of the duct bank, and meeting the stringent requirements of OSHA. JBCC also had to be diligent in our digging techniques as to not hit the numerous utilities that were crossing all over Lower Wacker Drive. Due to all of these utilities JBCC had to utilize three different types of shoring methods during construction, and they were trench boxes, steel plates with hydraulic speed shores, and timber lagging.
  • Underground Electrical Infrastructure: JBCC was responsible for installing all of the underground infrastructure required for the new power systems on Lower Wacker Drive. This included all of the service feeds from ComEd transformers to the various City Electric Rooms, Vent Rooms, and Bridge Electric Rooms. JBCC was also responsible for the installation of all of the service cable where we installed over 80,000 ft of 500 MCM 600 V fire rated cable to feed all of the various services.
  • Upper Wacker Drive Electrical Infrastructure: This work included the installation of all of the conduits which were attached to the underside of Upper Wacker Drive. Due to Upper Wacker Drive being a post tension deck, no drilling into the deck was allowed, so JBCC was responsible for the installation of one foot and two foot inserts which were poured into the PT deck. JBCC then installed over 80,000 ft of conduits ranging in size from ¾” to 4” the entire length of the project. Included in this work was also the installation of over 700 tunnel luminaires which are providing the light for the new Lower Wacker Drive.
  • Electrical Infrastructure: JBCC was responsible for constructing all of the new electrical infrastructure required to serve the various systems on Wacker Drive. This work included the construction of five new city electric rooms, the new construction of four bridge electric rooms (Jackson, Adams, Madison, & Washington), the modification of three bridge electric rooms (Van Buren, Monroe, & Randolph), the new construction of three new vent electric rooms (Adams, Washington West, & Washington East), the modification of five vent electric rooms (Wells, LaSalle, Clark, Dearborn, & State), and the installation of over 200,000 ft of specially made 2 hour fire rated electrical cable of various sizes.
  • City Electric Rooms: These rooms are the main services which feed the various lighting and traffic systems along Upper and Lower Wacker Drive. All of the individual traffic and lighting cabinets are each fed from a separate breaker on the main transfer switch within their respected room.
  • New Bridge Electric Rooms: These rooms are for the new services which feed all the electrical components that make the various bascule bridges moveable. The old bridges were fed off of CTA 600V DC feeds, the new rooms are fed off of a new ComEd 600V AC feed. As the bridge motors all run off DC power, JBCC installed 16 new rectifiers (4 at each new room) to convert the feed from AC to DC.
  • Vent Electric Rooms: JBCC was responsible for the installation of all the equipment necessary to power the new fans being installed along Lower Wacker Drive. Some equipment included automatic transfer switches, main service board, and the variable frequency drives (which provide direct power to the fan motors). Work also included a PC/PLC system which is responsible for monitoring the conditions inside the tunnels. This system also provides an interconnect so the rooms can communicate back to the OEMC center. JBCC was responsible for pulling over 20,000 ft of a special fire rated Fiber Optic cable to make this communication possible.
  • Submarine Cable Installation: In order for the new bridge rooms to be able to be operable from one side, JBCC was required to install up to 6 submarine cables at one bridge location. Working with the coast guard and the city of Chicago, JBCC was able to install new submarine cables at Jackson, Adams, Washington, and Madison bridges. In order to complete this JBCC set up two 1A trucks at the east and west sides and essentially pulled the cable from one end to the other, then lowering the cable into the river. Using divers JBCC inspected the condition of the cable to ensure they were lying flat and not overlapping each other.
  • Traffic Signals and Upper Lighting: JBCC completed the installation of new traffic signal equipment at all seven intersections along Upper Wacker from Randolph to Van Buren, new traffic equipment installed at Van Buren & Wells to add a contra flow right turn lane from Van Buren to Wells, and new traffic equipment at Wells & Harrison along with Harrison & Wacker/Franklin to coincide with the congress interchange opening. JBCC also installed all new architectural lighting along Upper Wacker Drive to match the lighting which was previously installed on the East/West section of Upper Wacker Drive. Due to the new lane configuration and clearer separation of the service lanes from the through lanes, JBCC installed new traffic signals at Lower Wacker & Adams, 20 S Lower Wacker Drive, Lower Wacker & the Monroe on Ramp, and 155 N Lower Wacker Drive. All of the intersections on Lower Wacker Drive JBCC was required to cut loops into the pavement for vehicle sensing, whereas all of the intersections along Upper Wacker Drive we were required to install cameras for sensing.
  • OEMC Radio System: Due to the new configuration of Wacker Drive, the OEMC radio signal was no longer able to reach certain parts of Lower Wacker Drive. JBCC was responsible to design and build a system which met the intent of the CDOT and OEMC specifications. JBCC first installed all of the necessary equipment inside the newly constructed Radio Room. We then installed approximately 10,000 ft of conduit attached to the deck of Wacker Drive from Van Buren to Columbus, installed approximately forty antennas at various locations along the conduit run, and then pulled a special Coaxial cable to connect all of the antennas back to the Radio Room. JBCC also installed two antennas, one at Upper Wacker & Clark and one at Upper Wacker & Monroe, to “catch” the signal and send it to the Bi-Directional Amplifiers (BDA) which were installed inside the Radio Room.
  • Completion:  Although there were numerous constraints, and a “No Budge” completion date of November 30, 2012, JBCC was able to successfully complete the project on time.

Congress Parkway Streetscape

congress

Project Description

Client: F.H. Paschen Construction
Location:  Chicago, Illinois
Year Completed:   2013
Contract Value: $5,000,000

John Burns Construction Company completed the electrical installation along Congress Parkway in Chicago, Illinois in 2013. The project included the modernization of traffic signal intersections and installation of decorative lights that is a fully programmable LED lighting system complete with over 600 LED fixtures.

The Challenges

  • JBCC recently completed the electrical installation along Congress Parkway from Wells Street to Michigan Avenue.
  • This was a very unique project that included the modernization of eight (8) Traffic Signal intersections and the installation of new decorative roadway lighting poles along Congress Parkway.
  • The highlight of the project is a fully programmable LED lighting system complete with over 600 LED fixtures.
  • Three different types of programmable architectural LED lighting fixtures were installed at various locations along the ½ mile stretch of Congress Parkway that leads from the Eisenhower Expressway into the heart of the loop.
  • Sixteen foot tall cylindrical decorative LED bollards were installed in the parkway median planters along the entire stretch of Congress Parkway. Each bollard consists of four sections of color changing LED tubes that has unlimited design effects.
  • The system includes over 100 LED fixtures that wash the wall under the Chicago Board of Trade.
  • This one of a kind LED lighting system can produce over 16 million different color combinations and includes different seasonal, holiday and special event programs.